Update production plan
PUT/api/projects/{project_id}/production-plans
Updates all submitted months and soft-deletes omitted ones. Dates use YYYY-MM, without duplicates, past months are ignored. Monthly values plus actual production must total 100%.
Time-based projects cannot be edited. When production planning by stream is enabled, saving the project plan also redistributes each stream's remaining production across these months.
Required permissions:
- production_plan.modify: allows editing projects where the user is PM or Account.
- production_plan.modify_other: additionally required for other projects.
Here the dedicated support page.
Request
Responses
- 200
- 400
- 401
- 403
- 404
- 409
- 412
Returns the saved current and future production plans, ordered by date.
Validation failed
Unauthorized
Forbidden
Not found
Invalid total percentage or a project with time-based progress.
Precondition failed